Hardwood flooring has no single acclimation time that applies to every product. Follow the manufacturer's requirements for the exact floor, then have the installer confirm that the material and jobsite are ready. The number of days since delivery is only part of that decision.
Before agreeing to delivery, get the installation guide for the flooring you are buying. Confirm the storage location and carton instructions with your installer. Those details belong in the plan before boxes arrive at your Montgomery County home.
Start with the exact flooring you are ordering
Two hardwood samples can have different constructions and installation requirements. Write down the manufacturer, collection, product code, and intended installation method. Keep those details with your estimate rather than relying on the showroom sample's color name alone.
For example, Mirage publishes separate installation guides for Solid, TruBalance, TruBalance Lite, Lock, and patterned floors. That is a useful reminder to match the instructions to the product you are ordering.
Ask the installer to identify the current guide and the sections that govern delivery, site preparation, and installation. If advice from a general article conflicts with that document, resolve the discrepancy with the manufacturer before work begins.
A Bjelin hardwood project in Bethesda
Our Bjelin Misty White project in Bethesda features floating hardened wood flooring in a long room with white walls and a sloped ceiling. The light finish and visible plank grain show how this wood product looks across a full room.

If you save this project for inspiration, include its product name when you visit either showroom. For your installation, have the exact Bjelin product's guide checked for carton handling, room conditions, and delivery timing.
Understand what acclimation is trying to achieve
Wood exchanges moisture with its surroundings. The National Wood Flooring Association's moisture guidance explains that humid conditions can cause wood to swell, while dry conditions can cause it to shrink. The environment remains relevant after the floor is installed.
Acclimation prepares the material for its intended conditions. An active leak or unsuitable subfloor needs its own correction before installation can proceed.
Confirm whether the cartons should stay closed
The advice to "open every box and spread the boards out" is not a universal instruction. Packaging is one of the details that must come from the selected product's guide.
For Mirage TruBalance Lite, the guide specifies at least 24 hours in unopened boxes in the installation room for temperature adjustment. It says to open the boxes at installation. That same guide requires the heating system to be operating and the specified room temperature to have been maintained for at least a week. These are separate requirements: a 24-hour product-temperature instruction does not replace the room-conditioning period or subfloor checks. Use this example only for the named product and confirm its current guide before installation.
Before delivery, ask:
- Where exactly should the cartons be placed?
- Must they remain sealed, and who decides when to open them?
- What storage arrangement does the product require?
- How will deliveries be kept out of household access routes?
- Who should be contacted if packaging arrives wet or damaged?
Keep the answers with the order so everyone handling the material has the same instructions.
Check the room, flooring, and subfloor separately
The room environment, the flooring, and the subfloor are not interchangeable measurements. Ask for a plain-language explanation of the checks relevant to your product and installation method.
| Part of the plan | Question to settle |
|---|---|
| Room conditions | What temperature and humidity requirements apply, and for how long? |
| Flooring material | What condition must the delivered product reach before installation? |
| Subfloor | Which inspection or moisture tests are required for this surface? |
| Records | Who records the results, and can you keep a copy? |
| Decision to proceed | Who confirms that the applicable requirements have been met? |
Have the installer explain the test method and the acceptable result for your floor. Keep that explanation with the readings so the decision to proceed has a clear basis.
Plan delivery around the renovation
If flooring is part of a larger remodel, list the work still happening in the rooms that will receive it. Tell the installer about unfinished painting or plastering, new concrete, and any known water problem. Ask which activities must be finished before delivery and which affect the installation date.
For a fall or winter project, discuss how the rooms will stay at the required indoor conditions throughout the work. If heating will be shut down or replaced during the renovation, settle the flooring sequence before booking delivery.
For a Montgomery County home with several levels, identify where each part of the order will be installed. Ask whether the proposed storage location is appropriate for those areas. Do not assume a convenient garage or spare room represents the conditions in every room receiving flooring.
Also separate delivery access from installation access. Cartons may arrive before the room is closed for work. Confirm the path through the home, who will move the material, and how your household will reach essential rooms in the meantime.
Our flooring cost guide covers broader estimate considerations. For scheduling, make sure delivery, preparation, inspection, and installation are described as separate steps where they need to be.
Agree on what happens if a check fails
Build a readiness check into the schedule. Ask what happens if the site does not meet the product requirements when the crew is due to begin.
Agree on who will explain the finding, arrange any corrective work, and set the next inspection. Ask how a revised date or additional cost would be approved.
Discuss those questions while comparing proposals. Subfloor conditions may only become visible after the existing floor comes up, so leave room to review any new work before it proceeds.
If you have a firm deadline for moving furniture back or hosting guests, tell the showroom team early. Ask how delivery, inspection, installation, and any required wait before room use fit that deadline.
Keep the product records after installation
Save the installation guide, warranty, product identifiers, and any agreed test or inspection records together. Ask which indoor conditions and care instructions apply once the room is back in use. Our floor-care guide is a general starting point, but the selected product's instructions remain important.
If you are still comparing constructions, read our engineered-hardwood explainer. For homes in Olney, Potomac, and throughout Montgomery County, bring your room plan and renovation schedule to either Olney or Potomac. You can also discuss your hardwood project with our team.
Header photo: warm wood-look flooring from our Urbana project gallery.
Related service
Explore hardwood flooring options
See the service pageMore reads
- Hardwood Installation
Hardwood Flooring in Olney, MD: Solid Above Grade, Engineered in the Basement
5 min read - Hardwood Flooring
Hardwood Flooring in Rockville: Solid, Engineered, or Refinish What's Already There
4 min read - Hardwood Refinishing
Refinish or Replace? A Hardwood Floor Guide for Aspen Hill Homes
7 min read - Flooring Planning
Silver Spring Condo Flooring: Rules, Sound, Subfloor, and Installation Logistics
8 min read